Hwy. 400 & Tiffin Street Overpass & Barrie Collingwood Railway Overhead – 720 Series II TBM, 5200 Pump Unit and 1548 Haul Unit

Project Name
Hwy. 400 & Tiffin Street Overpass & Barrie Collingwood Railway Overhead
Subcontractor
CRS Tunnelling
Location
Barrie, Ontario, Canada
Ground Conditions
Compacted Sand and Dirt
Akkerman Equipment
720 Series II TBM, 5200 Pump Unit and 1548 Haul Unit
Pipe
72-in. ID RCP
Total Length/Hard Rock Section
200-lf./200-lf.

Project Overview

CRS Tunnelling was selected subcontractor to work with Dufferin Construction on a Ministry of Transportation Project in the City of Barrie, Ontario, Canada.

The project involved the construction of a tunnel under Hwy. 400 installed by pipe jacking methods to install the RCP product pipe.

Challenges

• Construction adjacent to a watercourse containing protected aquatic species

• Protective soil erosion and sedimentation control measures to prevent impact

• Tunnelling occurred beneath a major expressway

• Limited cover over the crown of the tunnel

• Complex traffic control and staging plans

• Experienced tunneling expertise required to ensure correct levels of face support

Solution

• 720 Series II TBM and Tunnel Boring System

• Closed face cutter head to prevent subsidence

Outcome

• Successful installation with no settlement of the roadway surfaces or impeded traffic